How Long Does Sewer Line Replacement Take? Trenchless vs Digging

How Long Does Sewer Line Replacement Take? Trenchless vs Digging

sewer line replacement

If your sewer line is failing, you don’t just want a “range.” You want to know what this is going to do to your life.

Are we talking a day?

A week?

Am I going to have a torn-up yard for a month?

Will my toilets be out of service the whole time?

Let’s cut through the noise and answer the real question:

How long does trenchless sewer replacement take compared to digging a trench and replacing the pipe the old-school way?

The Quick Answer Most Homeowners Want

In a typical residential situation:

  • Trenchless sewer replacement: often 1 day, sometimes 2 days
  • Traditional digging (excavation): commonly 3–7 days, sometimes longer

That’s the simple answer. Now here’s the honest answer:

The method matters, but the site conditions matter more.
The reason trenchless is usually faster is because you’re not spending days digging the entire pipe run and then back-filling and rebuilding everything above it.

Why Trenchless Is Usually Faster Than Digging

Think about what slows a job down. It’s rarely the act of “putting pipe in the ground.”

It’s everything around it:

  • digging the full length of the line
  • managing dirt piles / hauling material
  • dealing with deep trenches safely
  • crossing driveways, landscaping, patios, retaining walls
  • restoration (and waiting on concrete/asphalt or other trades)

 

With trenchless, you’re typically working from two access points (small pits) instead of opening up a long trench. Less digging = less restoration = less time.

Typical timelines: Trenchless vs Digging

Trenchless sewer replacement timeline (most common):

Typical: 1–2 days
Sometimes: half-day to 3 days (depending on access and unknowns)

Trenchless usually includes methods like:

  • Pipe bursting (replacing the entire pipe by breaking the old one and pulling in a new pipe)
  • CIPP lining (rehabilitating the existing pipe from the inside, if the line qualifies)

 

If the pipe is collapsed, severely offset, or packed with roots to the point a camera can’t pass, pipe bursting is often the better “trenchless replacement” option.

Traditional excavation timeline (most common):

Typical: 3–7+ days
Sometimes: 1–2 weeks (especially if deep, under hardscape, or restoration is complex)

Excavation can move quickly in perfect conditions. But most properties aren’t “perfect conditions.”

What Actually Happens During A Trenchless Sewer Replacement (Step-By-Step)

Homeowners deserve to know what they’re paying for and what they’re about to live through. Here’s what a normal trenchless replacement looks like on-site.

1) Confirm the problem with a camera inspection

Before anyone quotes timeline, the line needs to be understood:

  • pipe material (clay, cast iron, Orangeburg, PVC, etc.)
  • where the pipe runs
  • whether it’s broken, “bellied”, offset, or collapsed
  • depth and access points

Time: usually 1–3 hours

2) Utility locates + job layout

Even if we’re “not digging much,” we still dig. That means utilities must be marked.

This step can affect your schedule more than the actual replacement.
If marks are delayed, the whole project moves.

3) Dig small access pits (not a trench)

Most trenchless replacements need:

  • an entry pit (where equipment sets)
  • an exit pit (or connection point)

Time: a few hours (varies by depth, soil, and access)

4) Install the new pipe (the part everyone imagines takes forever)

The actual “pull” is often not the longest part. Setup and proper connections matter just as much.

Time: often a few hours

5) Tie-ins, testing, backfill, cleanup

This is where good contractors separate themselves from sloppy ones:

  • correct connections
  • flow checks
  • compacting and clean backfill
  • a jobsite that doesn’t look like a tornado came through

 

Time: end of job day or next day

What Actually Happens During A Dig-And-Replace Job (And Why It Takes Longer)

Traditional excavation isn’t “bad.” Sometimes it’s the right call. But it’s usually slower because:

1) The trench is the project

Opening the trench is the largest time block:

  • digging the full run
  • keeping trench safe
  • dealing with groundwater / collapse risk
  • hauling spoils
  • working around obstacles
2) Restoration is the hidden timeline

A lot of contractors talk about replacement time but skip the part that matters to homeowners:

  • replacing topsoil
  • reseeding / straw
  • repairing landscaping beds
  • rebuilding patios, walkways, or retaining walls
  • driveway or sidewalk restoration

Even when pipe work is done, you might still be waiting on the “put it back like it was” stage.

The Biggest Reasons Sewer Replacement Takes Longer Than Expected

Whether you choose trenchless or digging, these are the usual timeline killers:

Utility locate delays

If locates aren’t complete, you’re waiting.

Access issues

Tight backyards, steep grades, fences, decks, and landscaping can slow setup and equipment placement.

Unknown depth or route

Older homes, additions, and DIY plumbing changes can make the line route unclear until verified.

Full collapse or severe offsets

Some trenchless methods require a passable line. If it’s completely collapsed in multiple places, you may need additional excavation at specific points.

Hardscape complications

Driveways, sidewalks, stone patios, pavers, retaining walls — these can turn a “simple job” into a multi-step restoration project.

When Digging Might Actually Be The Better Choice

Here’s the honest part that builds trust: trenchless isn’t the answer every single time.

Digging may be the smarter option when:

  • you need to change the route (bad slope, poor layout, repeated failures)
  • the line has multiple branches/tie-ins that need reworking
  • you’re already doing a major renovation and restoration is planned
  • there’s no practical way to set trenchless equipment safely

 

A contractor who only wants to sell trenchless will always steer you trenchless. A contractor who actually cares will tell you when it’s not the right fit.

The Disruption Comparison (What Most Homeowners Care About)

Trenchless: usually less disruption
  • smaller dig areas (often two pits)
  • less damage to yard and landscaping
  • shorter “no heavy water use” window
  • typically faster return to normal routines
Digging: more disruption, especially in finished areas
  • long trench across the yard
  • heavier equipment traffic
  • more cleanup and restoration steps
  • bigger chance of “surprises” once open

How To Get A Timeline You Can Trust (Questions To Ask)

If you want a realistic schedule, ask the contractor these questions and listen to how they answer:

  1. Have you camera-inspected the line? (If not, timeline is a guess.)
  2. Where are your access points? (Show me.)
  3. What could add days to this job? (They should have a list.)
  4. What restoration is included, and what is not?
  5. How long will sewer service be interrupted?
  6. Do you handle permits/inspections if required, or is that on me?

A contractor who answers clearly is usually a contractor who runs organized jobs

Bottom Line: Trenchless Is Commonly Faster Than Digging

If you want the cleanest rule of thumb:

  • Trenchless sewer replacement: commonly 1–2 days
  • Dig-and-replace excavation: commonly 3–7+ days, sometimes longer with restoration

 

The only way to get a timeline that’s truly accurate is to base it on:

  • a camera inspection
  • access and depth
  • restoration needs
  • utility locate timing

Looking For Help?

If you’re in Southwest Virginia  and you want an honest recommendation — trenchless vs digging — start with a camera inspection. Once the line is confirmed, we can tell you what the job will actually look like, how long it should take, and what could slow it down. Skiwi is here to help, give us a call!

Next Read

If you want to see exactly how pipe bursting works (and why it’s often the fastest trenchless option), read this next:

Pipe Bursting Explained: The Fastest Way to Replace Underground Pipes Without Digging
https://www.skiwipipebursting.com/pipe-bursting-explained-the-fastest-way-to-replace-underground-pipes-without-digging/

 

skiwi Pipe Bursting logo

More Posts

Cross‑section of a home septic system showing septic tank, distribution box, drainfield, and soil treatment with trees and blue water lines.
drain and sewer problems

Why Do Septic Systems Fail? 8 Common Causes

Why do septic systems fail? From overloaded drainfields and neglected tanks to damaged pipes and distribution problems, there are several possible causes. Learn the warning signs, what can lead to failure, and why properly diagnosing the problem should come before deciding on a repair.

Read More »
Blue wooden house with a peaked roof; beneath it, a cross-section reveals a network of blue plumbing pipes beneath the ground.
drain and sewer problems

Can My Underground Plumbing Be Rerouted?

A failing underground pipe doesn’t always have to be replaced along the exact same path. Depending on your property, sewer, water, or septic lines may be rerouted to avoid driveways, patios, structures, landscaping, or other obstacles. Here’s what determines whether rerouting is possible—and when it may be the smarter long-term solution.

Read More »
A bright hotel room with a white bed, two suitcases (blue and yellow) and a wooden chair by a window with potted plants nearby